This is the 51st edition of the newsletter that keeps you up to date with the progress of the Germany Beck junction works on the A19 in Fulford.
As we head towards the final weeks, works have been continuing on Landings Lane and the A19.
The concrete capping beam has progressed from Landings Lane and up the A19.
Stone and kerbs have been laid to Landings Lane in readiness for the next surfacing visit.
The deep combined sewer diversion in the A19 is almost complete.
During the next 2 weeks the sheet pile capping beam up the A19 will be completed together with the combined 450mm dia combined sewer diversion.
The brick wall to the top of the capping beam will commence on Landings Lane.
Pedestrians will continue to use the new eastern footpath while the western footpath remains closed until the end of the works.
Elsewhere on site we are continuing foul water and surface water drainage installation and preparing for new roads for the new residential development.
Please be assured that the different areas of works will be securely fenced at all times to ensure the safety of the public. We will be receiving deliveries to site this week. Each delivery will be guided into site by one of our employees once traffic and pedestrians are clear from the site entrance. Please be patient if you are held up for a short time whilst these manoeuvres take place. Pedestrians will be given right of way along the footpaths of Fordlands Road but please be aware of deliveries using the entrances to site off Fordlands Road on occasion
To receive our regular newsletter, keeping you up to date with the progress of the works as well as advance warning of activities that may affect traffic, you can join our mailing list. Please fill in your details below and tick the 'Add me to your mailing list' box.