Gateway 36

Gateway 36 Newsletter No 4

19 February 2021

Gateway 36 Newsletter No 4 Week commencing Monday 22nd February. First published Friday 19th February. 

Each fortnight, these e-newsletters will provide you with updates on progress, traffic management and any potential disruption surrounding the Gateway 36 development in Rockingham. Please note these works will be ongoing until Summer 2021. 

Progress, the past two weeks

Traffic management measures have been in place on Dearne Valley Parkway Westbound from Monday 11th January to enable the construction of a new access road off Shortwood Roundabout. 

Stone for the new access road has now been placed and compacted and kerbs have been laid, giving a clear indication of how the layout of the road will look upon completion.

We have continued to install surface water drainage systems in the new access road which will collect all surface water from the road via road gullies. Once the road gullies are installed, they will discharge into the newly formed attenuation pond. We have also commenced the installation of land drains which will discharge into the existing highway ditch upon completion.

On the Gateway 36 development, drainage works to install an outfall from the new attenuation pond have continued. 

The next two weeks

Please note current traffic management measures are to remain in place in the current layout with a single-lane closure for the westbound lane approaching and exiting Shortwood Roundabout for the next three-to-four weeks. Please contact RTS on 01724 848 246  if there is an out of hours emergency with the traffic management. 

Over the next two weeks we will install ducting for new incoming services on the new access road off Shortwood Roundabout, including communication and electric services. We will then install road gullies which will collect the surface water from the road upon completion. 

Once these works are complete, we will be able to lay tarmac on the new access road. This will enable us to open the new functionable entrance to site and hopefully minimise disruption to the residents of Hoyland.  

On the main site we will recommence major earthworks and continue work to form the attenuation ponds, including the installation of a pond liner and topsoil. This will form two large ponds which will hold surface water during periods of heavy rainfall.

How the new access road will look upon completion

Your site contacts

There are several ways you can contact the site team to report faults, voice any concerns or ask any questions you may have. 

The Gateway 36 scheme is managed by the following members of our experienced and highly approachable team: Tony Kilbane (Contracts Manager), Thomas Barrett (Site Manager), Mick McNiffe (Site Supervisor) and George Bagnall (Site Engineer). Please rest assured there will always be a representative on site during working hours should you have you questions about the scheme.

To contact Howard Civil Engineering remotely, please contact your Community Liaison Officer, Sophie Henderson, at 
rockingham@howardcivileng.co.uk or contact 07793654086.

Comment or Join our mailing list

To receive our regular newsletter, keeping you up to date with the progress of the works as well as advance warning of activities that may affect traffic, you can join our mailing list. Please fill in your details below and tick the 'Add me to your mailing list' box.

Add me to your mailing list