CASE STUDY
LOGIC
LEEDS
Logic Leeds is the largest ever warehouse development in Leeds (361,000ft² distribution unit) and Plot M was completed in January 2019. The main contractor was Derbyshire-based Bowmer + Kirkland.
![](https://e3k7tuej792.exactdn.com/wp-content/uploads/2024/05/Plot-M-Howard-Civil-Eng-Feb-2019.jpg?strip=all&lossy=1&sharp=1&ssl=1)
CLIENT: BOWMER + KIRKLAND
VALUE:
£4.2M
LOCATION:
LEEDS
CONTRACT PERIOD:
65 WEEKS
CONTRACT TYPE:
BESPOKE
![](https://e3k7tuej792.exactdn.com/wp-content/uploads/2024/05/Plot-M-Howard-Civil-Eng-Feb-2019-1.jpg?strip=all&lossy=1&sharp=1&ssl=1)
STUDY
LOGIC LEEDS
LOGIC LEEDS
BACKGROUND
Logic Leeds is the largest ever warehouse development in Leeds (361,000ft² distribution unit) and Plot M was completed in January 2019. The main contractor was Derbyshire-based Bowmer + Kirkland.
The warehouse is strategically located at the new gateway to Leeds, just half a mile west of Junction 45 of the M1. It is just one-and-a-half miles east of Leeds city centre and adjacent to the route of the East Leeds Link Road. The site has planning consent for a variety of uses including warehouse and distribution, industrial and supporting services. The consent allows for a total of 1.6 million ft² which was built specifically to the occupiers’ requirements.
Howard Civil Engineering was awarded the groundworks package which commenced in January 2018. The poor weather threw an additional challenge to our team who ultimately demobilised to remobilise in May 2018.
![gray-bg](https://e3k7tuej792.exactdn.com/wp-content/themes/cbd/img/gray-bg.jpg?strip=all&lossy=1&sharp=1&w=1920&ssl=1)
SCOPE OF WORK
Cropping
Cropping 1452 piles
Reinforced concrete foundations
861m³ reinforced concrete foundations
Surface water drainage
1,600m surface water drainage from 225mm – 900mm diameter, up to 5.5m deep
Foul water drainage
621m foul water drainage up to 4.5m deep
Gatic slot drain
500m Gatic slot drain
Turbosider surface water attenuation tank
2,600m³ capacity Turbosider surface water attenuation tank
Concrete external slabs
13,500m² concrete external slabs
Gravel paths
3,860m² gravel paths
Kerbs and channels
5,000m kerbs and channels
Carriageways
Preparation for carriageways and access routes throughout the site
Trenches and ducts
4,600m trenches and ducts for new service provisions
Video
FEATURED CASE STUDIES
![bg-yellow](https://e3k7tuej792.exactdn.com/wp-content/themes/cbd/img/bg-yellow.jpg?strip=all&lossy=1&sharp=1&w=1920&ssl=1)
![](https://e3k7tuej792.exactdn.com/wp-content/uploads/2024/04/Bingley-Street-ground-and-aerial-photos-Leeds-81-1024x576.jpg?strip=all&lossy=1&sharp=1&ssl=1)
TRUST US TO DELIVER YOUR PROJECT ON TIME AND ON BUDGET