CASE STUDY

BMW AND MINI DEALERSHIP

In 2014, Caddick Construction were awarded the contract to construct a new BMW and Mini Car Dealership in Leeds by their client, Pendragon Property Holdings.

The new dealership included the showrooms, offices, workshops, plant rooms, canteens, a new site entrance and installation of infrastructure works that include services, drainage, main estate roads and landscaping.

CLIENT: CADDICK CONSTRUCTION

VALUE:

£1.8M

LOCATION:

LEEDS

CONTRACT PERIOD:

11 MONTHS

CONTRACT
TYPE:

JCT STANDARD
BUILDING SUBCONTRACT

logo
CASE
STUDY

BMW AND
MINI DEALERSHIP

BMW AND MINI DEALERSHIP

BACKGROUND

In 2014, Caddick Construction were awarded the contract to construct a new BMW and Mini Car Dealership in Leeds by their client, Pendragon Property Holdings.

The new dealership included the showrooms, offices, workshops, plant rooms, canteens, a new site entrance and installation of infrastructure works that include services, drainage, main estate roads and landscaping.

Howard Civil Engineering was subsequently awarded the civil engineering and infrastructure packages.

gray-bg

SCOPE OF WORK

Excavation for pile caps and ground beams

350m³ blinding

413m³ in reinforced concrete foundations; ground beams, pile caps and floor slabs

2,200m surface water drainage in pipes upto 750mm diameter

220m ACO drainage channel

External works including 740m³ reinforced concrete structures, slabs and retaining walls

3,000m precast kerbs

6,500m² block paving on a AC32 dense base course

Street furniture