Howard Civil Engineering is delivering a £2m groundworks package on the initial phase of Leeds City Council’s General Needs Housing scheme for our longstanding client, Wates Group.
CLIENT: WATES CONSTRUCTION
VALUE:
£2M
LOCATION:
LEEDS
CONTRACT PERIOD:
52 WEEKS
CONTRACT TYPE:
LEEDS GENERAL NEEDS
BACKGROUND
Howard Civil Engineering is delivering a £2m groundworks package on the initial phase of Leeds City Council’s General Needs Housing scheme for our longstanding client, Wates Group.
This development of 41 homes in Seacroft is part of Leeds City Council’s Council House Growth Programme.
Due to significant topographical challenges on this site, intense planning and coordination was required to ensure the works are delivered safety and efficiently. This includes the installation of a precast concrete culvert almost 6m deep in the adopted highway to provide an attenuation solution.