CASE STUDY
COGDEN BECK
Cogden Beck was our first contract for North Yorkshire County Council and comprised the reconstruction of two collapsed bridges. The bridges collapsed in 2019 as a result of flooding and our client was granted a £3m funding award to repair the damages.
CLIENT: WILLMOTT DIXON
VALUE:
£2.25M
LOCATION:
ROTHERHAM
CONTRACT PERIOD:
63 WEEKS
CONTRACT TYPE:
BESPOKE
COGDEN BECK
BACKGROUND
Cogden Beck was our first contract for North Yorkshire County Council and comprised the reconstruction of two collapsed bridges. The bridges collapsed in 2019 as a result of flooding and our client was granted a £3m funding award to repair the damages.
This site was a Site of Specific Scientific Interest and, as a result, it was essential that the reconstruction was completed in a very short time period. Howard Civil Engineering was awarded the project in August 2020 and significant emphasis was placed on our ability to react and mobilise very quickly in order to meet the challenging deadlines.
SCOPE OF WORK
TRUST US TO DELIVER YOUR PROJECT ON TIME AND ON BUDGET