CASE STUDY
LEEDS GENERAL NEEDS
Howard Civil Engineering is delivering a £2m groundworks package on the initial phase of Leeds City Council’s General Needs Housing scheme for our longstanding client, Wates Group.

CLIENT: WATES CONSTRUCTION
VALUE:
£2M
LOCATION:
LEEDS
CONTRACT PERIOD:
52 WEEKS
CONTRACT TYPE:

STUDY
LEEDS GENERAL NEEDS
LEEDS GENERAL NEEDS
BACKGROUND
Howard Civil Engineering is delivering a £2m groundworks package on the initial phase of Leeds City Council’s General Needs Housing scheme for our longstanding client, Wates Group.
This development of 41 homes in Seacroft is part of Leeds City Council’s Council House Growth Programme.
Due to significant topographical challenges on this site, intense planning and coordination was required to ensure the works are delivered safety and efficiently. This includes the installation of a precast concrete culvert almost 6m deep in the adopted highway to provide an attenuation solution.

SCOPE OF WORK
Foundations and retaining walls
Delivery of foundations and retaining walls
Drainage works
Drainage works for S104 adoption including large attenuation solution
Services
Installation and diversion of services
External works
External works & Landscaping
Highways
S38 and S278 highways