CASE STUDY

HARWORTH BRICK FACTORY

Work is now complete on our third project for Persimmon Homes. The new brick factory is a flagship project for the group on a 14.76 acre site in Harworth. At full capacity, the facility produces circa 80 million brick per annum.

CLIENT: PERSIMMON HOMES

VALUE:

£2.6M

LOCATION:

DONCASTER

CONTRACT PERIOD:

11 MONTHS

CONTRACT TYPE:

BESPOKE

logo
CASE
STUDY

HARWORTH BRICK
FACTORY

HARWORTH BRICK FACTORY

BACKGROUND

Work is now complete on our third project for Persimmon Homes. The new brick factory is a flagship project for the group on a 14.76 acre site in Harworth. At full capacity, the facility produces circa 80 million brick per annum.

Our package of works consisted of the specialist machine foundations, foundations and slabs for the various portal frame buildings, the roads and sewers (including off site connections), and the external yards.

gray-bg

SCOPE OF WORK

Infrastructure

Brick manufacturing building

Curing chamber

Curing chamber annexed to above

Process plant and machinery

Internal factory process plant and machinery

Conveyor system

External sand bins, hoppers, mixing and batching, cement silos and associated conveyors

Working area

Suitable delivery, drop off, loading areas

Plant manoeuvring areas

Plant manoeuvring areas for scooper and hopper areas

Storage area

Storage area for finished product

Loading area

Loading area

Office buildings

Temporary office buildings

Fuelling and maintenance building

Fuelling and maintenance building

Separate fuelling and maintenance

Separate fuelling and maintenance area for the continued operation of fork lift trucks

Associated roads and footpaths

Associated roads and footpaths around site along with two weighbidges

Surface and foul water

Surface and foul water infrastructure including off site connections