CASE STUDY

GERMANY BECK S278 WORKS

Works to deliver this complex junction of the A19 are now complete. The new junction was required to facilitate Persimmon Homes’ 650 unit residential development in the fields to the east, locally known as Germany Beck.

CLIENT: PERSIMMON HOMES

VALUE:

£3.7 M

LOCATION:

FULFORD, YORK

CONTRACT PERIOD:

105 WEEKS

CONTRACT TYPE:

NEC OPTION A

logo
CASE
STUDY

GERMANY BECK
S278 WORKS

GERMANY BECK S278 WORKS

BACKGROUND

Works to deliver this complex junction of the A19 are now complete. The new junction was required to facilitate Persimmon Homes’ 650 unit residential development in the fields to the east, locally known as Germany Beck.

Many months of planning preceded the start in June 2016. The A19 is one of the main routes into York and is locally very sensitive with respect to several environmental issues. The new junction will now operate under traffic signal control, providing access to the new housing site but also to the community living within Fulford South. The highway scheme will in addition, provide flood protection to the A19.

Due to the sensitivity of the site, Howard Civil Engineering diligently kept all local interested residents and businesses informed of the progression of the junction works through a series of newsletters and a dedicated page on our website.

The works started on site in June 2016 and were completed in January 2019. A 25,000m³ flood alleviation earthworks package was completed over summer 2016 to provide compensatory volume for the anticipated flood water displaced by the creation of the junction within a low lying area.

gray-bg

SURROUNDING FACTORS

Requires IDB Sign Off

The presence of the Germany Beck watercourse within the site requiring IDB sign off for all adjacent works.

Water Voles

Water voles within the beck running along the periphery of the works.

Archaeology

Archaeology watching brief present for all works at formation.

Historically Important Existing Structures

The works took place in proximity to historically important existing structures.

Local Residents

The works took place within close proximity of local residents in the area.

Invasive Weeds

Himalayan Balsam in profusion on site.

Community Liaison Programme

Community liaison programme to keep local residents and users of the A19 informed about progress and disruption.

Bats

Species of bats existed in proximity of the works, and therefore needed to be considered.

Access To Local Residential Areas

Road works phased to ensure access to local residential areas and individual properties.

SCOPE OF WORKS

Flood Alleviation Earthworks

25,000m³ flood alleviation earthworks package including inlet and outlet structures.

Retaining Wall

Design and installation of a £500k 5m high sheet piled retaining wall with buttresses, relieving slab and capping beam.

Traffic Management

Extensive traffic management programme to manage anticipated disruption to peak traffic flows.

Complex Phasing

Complex phasing due to the difference in levels between online and offline works.

Junction

Junction located on main pedestrian routes to local primary and secondary schools.

New Traffic Light Junction

Provision of new vehicular and pedestrian traffic light-controlled junction.

Video

TRUST US TO DELIVER YOUR PROJECT ON TIME AND ON BUDGET