Howard Civil Engineering were employed by our new client, Hollycroft Construction to deliver the reinforced concrete frame.
Due to obstructions in the ground, the piling and groundworks (undertaken by others) took longer than initially envisaged and we worked with our client to establish a delivery that maintained the main contract programme. Our openness and flexibility around programme and delivery was a key factor with our client deciding to progress with Howard Civil Engineering.
Due to the site constraints, we employed a ‘just in time’ delivery strategy to best manage the limited space onsite and overcome the challenging site logistics. Furthermore, with our head office and plant yard just over three miles away we were able to use this valuable off site space for prefabricating steel and constructing formwork/falsework.