BACKGROUND

Following extensive negotiation and value engineering sessions, Howard Civil Engineering was awarded the groundworks and structures package for the £20m project to build The Phoenix Partnership’s new head office in Horsforth, Leeds.

The project saw ISG construct an 85,000 sq ft head office building for The Phoenix Partnership on a sloping site, which incorporated two levels of under croft car parking facilities.

A key feature of the building is the virtual absence of columns across the four main floor plates, with ISG installing a series of delta beams which span up to 17m within the main office areas to provide uninterrupted sight lines from front to rear. At ground floor level, The Phoenix Partnership’s new headquarters boasts a high-specification main reception area with a double height, light filled atrium, and a combination of cellular and open-plan office accommodation to the rear of the building.

The project represented our first project in partnership with ISG.

gray-bg

SCOPE OF WORK

Planning and administration

High-intensity planning and programming exercise required to a restricted and challenging site

Civil engineering and groundworks

Extensive excavation and mass filling operations, in very poor ground conditions, in advance of the main basement construction

Reinforced concrete works

The construction of an irregular two-storey underground car park, consisting of reinforced concrete retaining wall bases with wall stems 6.0m in height. A 2.0m deep single central core foundation with 700m³ on concrete was constructed incorporating a tower crane base

Reinforced concrete ground

Bearing floor slabs were constructed at basement level

External works

Kerbing, paving and block paving to external pedestrian areas

Drainage

Yorkshire Water sewer diversions in advance of main project commencement; installation of tubosider surface water attenuation tank; Internal and external drainage installation

Highways and surfacing

Access road and car park, sub-base build up and tarmac surfacing