CASE STUDY

BRADFORD ROYAL INFIRMARY

In March 2015, BAM Construction was appointed by Bradford Teaching Hospitals NHS Foundation Trust to deliver a £20m three-storey ward block development at Bradford Royal Infirmary.

CLIENT: BAM CONSTRUCTION

VALUE:

£1.5M

LOCATION:

BRADFORD

CONTRACT PERIOD:

10 WEEKS

CONTRACT
TYPE:

NEC3 SUBCONTRACT OPTION A

logo
CASE
STUDY

BRADFORD
ROYAL INFIRMARY

BRADFORD ROYAL INFIRMARY

BACKGROUND

In March 2015, BAM Construction was appointed by Bradford Teaching Hospitals NHS Foundation Trust to deliver a £20m three-storey ward block development at Bradford Royal Infirmary.

The works included paediatric and elderly patient wards, a critical care unit, retail, car parking, accessible access routes and roadways for the hospital.

The project was handed over to the hospital in March 2017.

gray-bg

SCOPE OF WORK

Civil engineering and substructure works to form new temporary entrance building into the hospital

Excavation for basement works

Basement slabs and walls

Suspended upper floor reinforced concrete slabs and roof

External works retaining walls and steps to cater for differences in levels across the site

External works kerbs, Marshalls ‘Mini Beany’ and ‘Pavedrain’, paving and street furniture

Surface and foul water drainage

3 Stormbloc attenuation tanks

Service duct infrastructure

Construction immediately adjacent to a live hospital environment

Extremely tight site footprint with topographical challenges

VIDEO