CASE STUDY

GREENHEAD AND BEECHCLIFFE HIGH SCHOOL

This secondary school is sited on the existing campus is part of the government’s commitment to refurbishing and re-building all new high schools throughout the country through the BSF program.

CLIENT: EDUCO

VALUE:

£5.2M

LOCATION:

KEIGHLEY

CONTRACT PERIOD:

100 WEEKS

CONTRACT TYPE:

BESPOKE

logo
CASE
STUDY

GREENHEAD AND BEECHCLIFFE
HIGH SCHOOL

GREENHEAD AND BEECHCLIFFE HIGH SCHOOL

BACKGROUND

This secondary school is sited on the existing campus is part of the government’s commitment to refurbishing and re-building all new high schools throughout the country through the BSF program.

This entailed a £47m development of the campus which was awarded to Educo through a negotiated tender process. Due to a successful historical partnership with Educo, Howard Civil Engineering was awarded the contract for all groundworks and infrastructure including hard landscaping.

gray-bg

SCOPE OF WORK

Early engagement to enable design development consultation

Practical build and product alternatives provided significant cost and time efficiencies

Live school environment

Soil strip, major cut, fill and re-engineering (70,000m³)

278 works traffic management

Construction of all new highways and car parks including macadam

Construction of all reinforced concrete structures including retaining walls over 5m high

Formation of sports pitches including hockey, tennis, football and rugby to Sport England standards

Extensive paths and feature paving

Comprehensive drainage network including large diameter storage tanks (6,000m³)

Petrol interceptors and many kilometres of ducting and trenching to facilitate services

VIDEO

TRUST US TO DELIVER YOUR PROJECT ON TIME AND ON BUDGET