CASE STUDY

SCARBOROUGH HOSPITAL

A £47m contract to improve Scarborough Hospital is being undertaken by Integrated Health Projects, a joint venture between Sir Robert McAlpine and VINCI Construction.

CLIENT: INTEGRATED HEALTH PROJECTS

VALUE:

£5M

LOCATION:

SCARBOROUGH

CONTRACT PERIOD:

50 WEEKS

CONTRACT TYPE:

logo
CASE
STUDY

SCARBOROUGH HOSPITAL

SCARBOROUGH HOSPITAL

BACKGROUND

A £47m contract to improve Scarborough Hospital is being undertaken by Integrated Health Projects, a joint venture between Sir Robert McAlpine and VINCI Construction.

The overall project includes the construction of a new two-storey building, which will combine and expand the existing Accident and Emergency department and acute medical unit, and the improvement of site-wide infrastructure such as the electrical systems, ventilation, and drainage.

This is the largest capital scheme ever undertaken by York and Scarborough Hospitals NHS Foundation Trust.

Following our recent improvement works at Huddersfield Royal Infirmary for VINCI, Howard Civil Engineering was approached by Integrated Health Projects to support them on this new project.

Due to the location of this project, we are looking forward to employing primarily local subcontractors and suppliers whilst undertaking work at Scarborough Hospital.

Howard Civil Engineering procured this project via the ProCure22 Framework.

A virtual tour of the new two-storey building can be taken here.

gray-bg

SCOPE OF WORK

Enabling works

Enabling works including service diversions

Relocation

Relocation of existing helipad

Working in a live hospital environment

Working in a live hospital environment, maintaining access for pedestrians and vehicles and avoiding existing services

Surface and foul water drainage

Installation of new surface and foul water drainage to service the new extension including two large geo-cellular attenuation tanks

Pile caps and ground beams

Installation of pile caps and ground beams to the new hospital extension

Reinforced concrete frame

Construction of three-storey reinforced concrete frame extension for a new Accident and Emergency ward

Construction of two lift and stair cores

Construction of two lift and stair cores with extensive temporary works requirements

Car park

Installation of new car park to enable Integrated Health Projects’ site compound and setup

Concrete foundations and frame

Over 4000m³ of concrete in the foundations and frame

tonnes of reinforcement

800 tonnes of reinforcement will be installed in the foundations and frame

Drainage

Installation of 1600m of drainage up to 5m deep

Service ducting

Installation of 1000m of service ducting

Kerbing

Over 2000m of kerbing to be installed