Otley Road Newsletter 6

17 January 2019

Otley Road Roadworks. Newsletter 6. Week commencing Monday 14th January

This is the sixth newsletter, providing you with information regarding the road works on Otley Road for the new Charles Church Residential Development.

Since returning from the Christmas break we have continued with the road widening works opposite the site entrance under 2 way traffic signals.

We have progressed with the carriageway construction to the west of the entrance and installed gulleys and sleeves for the lamp posts.

NIGHT TIME ROAD CLOSURES BOOKED FOR 5 NIGHTS FROM WEDNESDAY 16TH JANUARY.

On the night of Wednesday 16th January we will be returning to the junction with Beckwith Head Road to complete the foul sewer rising main connection into an existing foul sewer located within the junction.

Because of the space we need to carry this out we need to temporarily fully close Otley Road. To minimize the inconvenience to local traffic and businesses we will be carrying out these works at night only.

The road closures are booked for 5 nights, Wednesday (16th) night, Thursday, Friday, Saturday, and Sunday nights, from 7pm until 6am.

The agreed diversion route is via Beckwith Head Road, Howhill Quarry Road and Howhill Road.

Access to businesses and residences on the section of road that will be closed will be available from the Howhill Road end.


 

Comment or Join our mailing list

To receive our regular newsletter, keeping you up to date with the progress of the works as well as advance warning of activities that may affect traffic, you can join our mailing list. Please fill in your details below and tick the 'Add me to your mailing list' box.

Add me to your mailing list

Trust us to deliver your project on time and on budget