Germany Beck Newsletter 50

30 April 2018

Weeks 98 & 99 commencing Monday 30th April 2018 

This is the 50th edition of the newsletter that keeps you up to date with the progress of the Germany Beck junction works on the A19 in Fulford.

Works have been progressing to Landings Lane and the A19 this week.
We have been placing compacted stone to the realigned section of Landings Lane and have laid a concrete bed along the sheet piled wall in preparation for installing the capping beam next week. The concrete kerb foundation has also been cast.

On the A19 the YW water main diversion is now complete and we have been breaking out the carriageway in preparation to divert the existing combined sewer pipe into the new road.

Elsewhere on site we have commenced the copings to the top of the brick wall and have been spreading topsoil to the embankments ready for planting

During the next 2 weeks we will be installing the kerbs and the sheet pile capping beam to Landings Lane.

We will be carrying out the 450mm dia combined sewer diversion in the A19.

The copings to the top of the brick wall will progress throughout the week.

The planting of trees and shrubs to the spine road embankment will continue.

Pedestrians will continue to use the new eastern footpath while the western footpath remains closed until the end of the works.

Elsewhere on site we are continuing the deep drainage installation for the new residential development.

NO TEMPORARY TRAFFIC MANAGEMENT ANTICIPATED ON A19 FOR THE NEXT 2 WEEKS  
  

New A19 footpath route

Safety for children and the wider public.

Please be assured that the different areas of works will be securely fenced at all times to ensure the safety of the public.
We will be receiving deliveries to site this week. Each delivery will be guided into site by one of our employees once traffic and pedestrians are clear from the site entrance. Please be patient if you are held up for a short time whilst these manoeuvres take place.
Pedestrians will be given right of way along the footpaths of Fordlands Road but please be aware of deliveries using the entrances to site off Fordlands Road on occasion.
 

Comment or Join our mailing list

To receive our regular newsletter, keeping you up to date with the progress of the works as well as advance warning of activities that may affect traffic, you can join our mailing list. Please fill in your details below and tick the 'Add me to your mailing list' box.

Add me to your mailing list

Trust us to deliver your project on time and on budget