Germany Beck

Germany Beck Newsletter 34

08 September 2017

Weeks 66 & 67 commencing Monday 11th September 2017  

This is the 34th edition of the newsletter that keeps you up to date with the progress of the Germany Beck junction works on the A19 in Fulford. 

During the past two weeks we have been upfilling the next section of the spine road with stone to bring the embankment up to level before we commence the kerbline and gullies.

We have also been reconstructing the existing combined sewer manhole adjacent to Fordlands Road.

The brickwork walls to the retaining wall parapets have continued to the east of Fordlands Road. Scaffolding has been erected to commence the brickwork on the west side of Fordlands Road

We have laid drainage pipes across Germany Lane and reopened the lane to pedestrians.

Northern Gas have ceased their work to locate the medium pressure gas main on the A19. 

  

  

 During the next 2 weeks we will be  -  

  • Continuing brickwork walls to the sheet-piled retaining walls to the east and west of Fordlands Road
  • Progressing the spine road roadworks with kerbs and gullies to the east of Fordlands Road.
  • Installing BT Chambers 
  • Constructing the footpath to the west of Fordlands Road

The closure of the eastern footpath on the A19 remains in place. 

 

 

Safety for children and the wider public. 

Please be assured that the different areas of works will be securely fenced at all times to ensure the safety of the public.

We will be receiving deliveries to site this week. Each delivery will be guided into site by one of our employees once traffic and pedestrians are clear from the site entrance. Please be patient if you are held up for a short time whilst these manoeuvres take place.

Pedestrians will be given right of way along the footpaths of Fordlands Road but please be aware of deliveries using the entrances to site off Fordlands Road on occasion. 

Comment or Join our mailing list

To receive our regular newsletter, keeping you up to date with the progress of the works as well as advance warning of activities that may affect traffic, you can join our mailing list. Please fill in your details below and tick the 'Add me to your mailing list' box.

Add me to your mailing list

Trust us to deliver your project on time and on budget