Weeks 60 & 61 commencing Monday 31st July 2017 

This is the 31st edition of the newsletter that keeps you up to date with the progress of the Germany Beck junction works on the A19 in Fulford.
The water main diversion on the A19 is now complete. A medium pressure gas main diversion has been delayed and has hence resulted in a break in the use of temporary traffic lights on the A19.
The brickwork walls to the top of the sheet piled retaining walls have continued, along with the construction of the footpaths to the east of Fordlands Road

During the next 2 weeks we will be - 

• Constructing footpaths to the east of Fordlands Road
• Continuing brickwork walls to the sheet-piled retaining walls
• Continuing installation of the elliptical drainage pipes within the spine road embankment.


The closure of the eastern footpath on the A19 remains in place.

Safety for children and the wider public.

Please be assured that the different areas of works will be securely fenced at all times to ensure the safety of the public.
We will be receiving deliveries to site this week. Each delivery will be guided into site by one of our employees once traffic and pedestrians are clear from the site entrance. Please be patient if you are held up for a short time whilst these manoeuvres take place.
Pedestrians will be given right of way along the footpaths of Fordlands Road but please be aware of deliveries using the entrances to site off Fordlands Road on occasion.
 

Comment or Join our mailing list

To receive our regular newsletter, keeping you up to date with the progress of the works as well as advance warning of activities that may affect traffic, you can join our mailing list. Please fill in your details below and tick the 'Add me to your mailing list' box.

Add me to your mailing list

Trust us to deliver your project on time and on budget