Gateway 36 Newsletter No 9

29 April 2021

Gateway 36 Newsletter No 9 Week commencing Monday 3rd May. First published Friday 30th April. 

Welcome to the Gateway 36 e-newsletter. Each fortnight, these e-newsletters will provide you with updates on progress, traffic management and any potential disruption surrounding the Gateway 36 development in Rockingham. Please note these works will be ongoing until Summer 2021.

Progress, the past two weeks

Along Dearne Valley Parkway to the west, we have continued to form the new S278 roundabout which will facilitate entry to Phase 3 of the Gateway 36 scheme. Traffic management measures to close lanes are now in place in this area and surface water drainage installation is ongoing on both sides of Dearne Valley Parkway.

Both attenuation ponds on Phase 2 of the scheme are now complete, with pre-seed erosion control matting now visible as the finish surface.

Major earthworks have continued on the main development of site.

The next two weeks

This new traffic management layout will be in place long-term whilst work to construct the new roundabout is ongoing.

Should you experience or witness an out-of-hours emergency regarding the traffic management measures in place, please call RTS on 01724 848 246.

Over the next two weeks, work to form the new S278 roundabout will continue on both sides of Dearne Valley Parkway including earthworks and surface water drainage installation. We will also backfill the existing highway ditch and prepare for the new carriageway with stone, ducting and kerbs planning to be installed in the coming weeks.

On the main development site, earthworks will continue.

All works are scheduled to be complete for summer 2021. 

Gateway 36: A Bird's Eye View

Earlier this month, we took drone footage of ongoing works at Gateway 36 which highlight the scale of the works and offers a greater bird's eye view of this mammoth project. Have a watch below!

 

Watch on YouTube

How the new access road will look upon completion

How the new S278 roundabout will look upon completion

Your site contacts

There are several ways you can contact the site team to report faults, voice any concerns or ask any questions you may have.

The Gateway 36 scheme is managed by the following members of our experienced and highly approachable team: Tony Kilbane (Contracts Manager), Thomas Barrett (Site Manager), Steve Thackray (Site Supervisor) and George Bagnall (Site Engineer). Please rest assured there will always be a representative on site during working hours should you have you questions about the scheme.

To contact Howard Civil Engineering remotely, please contact your Community Liaison Officer, Sophie Henderson, at rockingham@howardcivileng.co.uk or contact 07793654086.

Comment or Join our mailing list

To receive our regular newsletter, keeping you up to date with the progress of the works as well as advance warning of activities that may affect traffic, you can join our mailing list. Please fill in your details below and tick the 'Add me to your mailing list' box.

Add me to your mailing list

Trust us to deliver your project on time and on budget