Gateway 36 Newsletter No 5 Week commencing Monday 8th March. First published Friday 5th March. 

Welcome to the Gateway 36 e-newsletter. Each fortnight, these e-newsletters will provide you with updates on progress, traffic management and any potential disruption surrounding the Gateway 36 development in Rockingham. Please note these works will be ongoing until Summer 2021. 

Progress, the past two weeks

Traffic management measures have been in place on Dearne Valley Parkway Westbound from Monday 11th January to enable the construction of a new access road off Shortwood Roundabout. 

Works have continued to form this new access road, including the laying of stone, kerbs and gullies. This work will continue to progress and will include the installation of ducting for incoming services (such as street lighting, electric, water mains) and the final trimming of stone ahead of tarmac being laid later this month.

We have also commenced works to form the new S278 roundabout which will facilitate Phase 3 of the Gateway 36 scheme adjacent to the east-bound Dearne Valley Parkway.

On the main Gateway 36 development, we have recommenced major earthworks and have continued drainage works such as the installation of an outfall from the new attenuation pond and a ditch diversion from the western side of the site to the existing pond.

The next two weeks

Please note current traffic management measures are to remain in place in the current layout with a single-lane closure for the westbound lane approaching and exiting Shortwood Roundabout for the next three-to-four weeks. Please contact RTS on 01724 848 246 if there is an out of hours emergency with the traffic management. 

Over the next two weeks we will continue work to form the new access road off Shortwood Roundabout. Once these works are complete, we will be able to lay tarmac on the new access road. This will enable us to open the new functionable entrance to site and hopefully minimise disruption to the residents of Hoyland.  

We will also continue work to form the new S278 roundabout which will include the installation of surface water drainage. This installation will involve pre-case concrete headwalls and 600mm concrete pipes which will collect surface water from the new roundabout once it is in operation.

On the main site, earthworks and work to form the new attenuation ponds will continue as normal. We expect the pond liner and topsoil works to be carried out in April to complete both ponds. 

How the new access road will look upon completion

Your site contacts

There are several ways you can contact the site team to report faults, voice any concerns or ask any questions you may have.

The Gateway 36 scheme is managed by the following members of our experienced and highly approachable team: Tony Kilbane (Contracts Manager), Thomas Barrett (Site Manager), Mick McNiffe (Site Supervisor) and George Bagnall (Site Engineer). Please rest assured there will always be a representative on site during working hours should you have you questions about the scheme.

To contact Howard Civil Engineering remotely, please contact your Community Liaison Officer, Sophie Henderson, at rockingham@howardcivileng.co.uk or contact 07793654086.

Comment or Join our mailing list

To receive our regular newsletter, keeping you up to date with the progress of the works as well as advance warning of activities that may affect traffic, you can join our mailing list. Please fill in your details below and tick the 'Add me to your mailing list' box.

Add me to your mailing list

Trust us to deliver your project on time and on budget