Gateway 36 Newsletter No 12 Week commencing Monday 14th June. First published Friday 11th June.

Welcome to the Gateway 36 e-newsletter. Each fortnight, these e-newsletters will provide you with updates on progress, traffic management and any potential disruption surrounding the Gateway 36 development in Rockingham. Please note these works will be ongoing until Summer 2021. 

Progress, the past two weeks

We have continued to form the new S278 roundabout along the western side of Dearne Valley Parkway which will facilitate entry to Phase 3 of the Gateway 36 scheme. Traffic management measures to close lanes remain in place in this area.

Major earthworks have continued on the main development of site.

The next two weeks

This new traffic management layout will be in place long-term whilst work to construct the new roundabout is ongoing.

Should you experience or witness an out-of-hours emergency regarding the traffic management measures in place, please call RTS on 01724 848 246. 

Over the next two weeks, work to form the new S278 roundabout will continue on both sides of Dearne Valley Parkway as we prepare the new carriageway for surfacing. Works will include the placement of stone and ducting for incoming service utilities and diversions. Following these works, in the near future, kerbs and tarmac will be laid, and new street lighting and signage will be erected.

On the main development site, earthworks will continue.

All works are scheduled to be complete for summer 2021.

We are pleased to say that throughout the month of May, Howard Civil engineering offset 105.74mt CO2e on this site - achieving CCB Gold! This mitigates the use of 41,533 litres of Gasoil for the same period. This has been compensated for by investing in both the Katingan Peatland Reforestation and Conservation Project and the 86 MW Hydro Project in Himachal Pradesh.

How the new access road will look upon completion

How the new S278 roundabout will look upon completion

Your site contacts

There are several ways you can contact the site team to report faults, voice any concerns or ask any questions you may have. 

The Gateway 36 scheme is managed by the following members of our experienced and highly approachable team: Tony Kilbane (Contracts Manager), Thomas Barrett (Site Manager), Steve Thackray (Site Supervisor) and George Bagnall (Site Engineer). Please rest assured there will always be a representative on site during working hours should you have you questions about the scheme.

To contact Howard Civil Engineering remotely, please contact your Community Liaison Officer, Sophie Henderson, at rockingham@howardcivileng.co.uk or contact 07793654086.

Comment or Join our mailing list

To receive our regular newsletter, keeping you up to date with the progress of the works as well as advance warning of activities that may affect traffic, you can join our mailing list. Please fill in your details below and tick the 'Add me to your mailing list' box.

Add me to your mailing list

Trust us to deliver your project on time and on budget