Skegness Academy

Client: Balfour Beatty

Value: £1,250,000
Location: Skegness
Contract Period: 66 weeks
Contract Type: BSF Bespoke Contract

Background:

Howard Civil Engineering Ltd supported Balfour Beatty in building the £22m Skegness Academy. The Academy replaced the St Clements College and The Earl of Scarborough High.

The programme included the demolition of many buildings and the refurbishment of other buildings. As well as state of the art accommodation for over 1300 pupils, a multi use games area and a long jump pit have also been constructed. The Skegness Academy was a finalist in the State School of the Year category at the prestigious Aviva and Daily Telegraph School Sport Matters Awards.

The construction programme commenced in May 2011 and was successfully handed over in July 2013.

Scope Of Works:

  • Live School environment
  • Ground beams and Pile Caps
  • External works and Hard Landscaping
  • Early involvement allowed fabrication of retaining wall to be done off-site

Testimonial:

"I have worked with Howards on a previous project where I found them to be diligent effcient with Health & Safety, so important to Balfour Beatty always at the forefront of all operations. They have again excelled in all areas and I look forward to out next project"

James Beardmore, Quantity Surveyor. Balfour Betty 

Accreditations

Trust us to deliver your project on time and on budget