Howard Civil Engineering commenced work at this site off Penny Pot Lane for Persimmon Homes in July 2018.
King Edwin Park is a new development of apartments and two, three, four and five-bedroom homes situated within Harrogate. The works awarded to Howard Civil Engineering include the S278 Works widening of Penny Pot Lane, introducing a new filter lane into the site. The site surface water outfall connection is to be installed withinthe existing Penny Pot Lane, under a road closure due to the width of the road, out-falling into a surface water course.
Work commenced on site with the creation of a temporary site entrance. The road and sewers package followed including 5m deep 1800mm dia attenuation pipes outfalling into a pond attenuation. The S278 works commenced in October after the 12 week notice for the TTRO application to close the road.
• Provision of adopted infrastructure for a 233 plot scheme in Harrogate • Provision of S278 Works additional filter lane and traffic islands on Penny Pot Lane • TTRO applications for speed limit reductions, temporary traffic signals and road closures • Liaison with NYCC and adjacent developers and utility providers to minimise disruption to Harrogate traffic • 2900m SW and FW 150mm dia to 2100mm dia drainage up to 5m deep • Adopted FW 6m deep pumping station • Installation of carriageway to base course • 500m SW installed within Penny Pot Lane under road closure and connection to existing SW watercourse • Shallow high pressure gas main stretches diagonally across site.
Penny Pot Lane will be closed from Monday 3rd August for four weeks as we continue works for Persimmon Homes. Read more in our latest newsletter: https://t.co/fCTbXPkBDa #harrogate #loveconstruction @HandpickedHgte @Harrogatebc @northyorkscc @StrayFM pic.twitter.com/CTHOHYNEZD — Howard Civil Eng (@HowardCivilEng) July 14, 2020
Penny Pot Lane will be closed from Monday 3rd August for four weeks as we continue works for Persimmon Homes. Read more in our latest newsletter: https://t.co/fCTbXPkBDa #harrogate #loveconstruction @HandpickedHgte @Harrogatebc @northyorkscc @StrayFM pic.twitter.com/CTHOHYNEZD
0.3%
AFR in October 2020
0.5%
IFR in October 2020
836,000
hours since last reportable incident
100%
of our engineers have HNC qualifications
of our managers have a minimum of 5 day SMSTS training