Hull Bonus Arena

Client: BAM Construction

Value: £1.8m
Location: Hull
Contract Period: 58 weeks
Contract Type: NEC3 Subcontract Option A

Background

Howard Civil Engineering commenced work on this site in December 2016 after being awarded a contract to undertake the foundations and ground floor slab, stair and lift core, drainage and hard landscaping and street furniture. The last pour to the auditorium floor in July 2017 marked the end of the first phase of our works.

Utilising a proven approach, we adopted a strategy of progressing the site to finished binder course level prior to programmed steel erection date. This was a strategic decision on Howard Civil Engineering's behalf to successfully remove the need for temporary hardstandings and subsequently offer significant financial savings for BAM.

Scope of works

  • 1185m foul and surface water drainage up to 575mm in diameter up to 3m deep
  • Installation 425m drainage kerb or slot drain
  • Installation of 2 interceptors
  • 600m³ modular attentuation system 
  • Cropping 500, 600mm diameter piles
  • 1000m³ in pile caps and ground beams
  • 2000m³ in power floated ground floor slabs

 

More from Hull Bonus Arena

Trust us to deliver your project on time and on budget