In 2014 Caddick Construction were awarded the contract to construct a new BMW and Mini Car Dealership in Leeds by their Client, Pendragon Property Holdings Ltd

The new dealership included the showrooms, offices, workshops, plant rooms, canteens, a new site entrance and installation of infrastructure works that include services, drainage, main estate roads and landscaping.

Howard Civil Engineering were subsequently awarded the civils and infrastructure packages.

Scope of works

  • Excavation for pile caps and ground beams
  • 350m3 blinding
  • 413m3 in RC foundations; ground beams, pile caps and floor slabs
  • 2,200m surface water drainage in pipes upto 750mm diameter
  • 220m ACO drainage channel
  • External works including 740m3 RC structures, slabs and retaining walls
  • 3,000m precast kerbs
  • 6,500m2 block paving on a AC32 dense base course
  • Street furniture

Accreditations